from pv journal in Spain

Madrid-based Acciona Energía has accomplished its second hybrid renewable technology facility in Spain with the development of a 19.7 MWp photovoltaic plant on the website of its 26 MW Peralejo wind farm, within the cities of Villalba del Rey and Tinajas, in Cuenca. The website will generate 37 GWh of fresh electrical energy per 12 months.

Peralejo is the corporate’s second hybrid challenge. Hybridization allows photo voltaic and wind fields to make use of the identical grid connection level.

In January 2024, Acciona commissioned its first hybrid challenge, the 29.4 MWp photo voltaic and 36 MW wind Escepar website in Villalba del Rey. The firm can also be creating the 50 MWp Bolarque photovoltaic plant in Tinajas. Acciona Energía is selling one other hybrid challenge in Granada, as pv journal reported, a 29.54 MW photovoltaic plant might be hybridized with the 30 MW Los Morrones wind farm, which was launched in 2008 and is situated within the cities of Baza and Zújar.

Acciona Energía mentioned pv journal it has 1.8 GW of hybridization initiatives within the pipeline.

In phrases of storage, the portfolio is 2.4 GW, of which 400 MW might be constructed within the United States.

By 2025, the corporate plans to construct 83 MW of photo voltaic technology capability within the Dominican Republic, at its Pedro Corto challenge, and 153 MW in India, with its Juna website. In 2026, Acciona will construct 48 MW of photo voltaic capability within the Viscofan challenge in Spain, 225 MW in two initiatives within the United States – with one other 115 MW to be added in 2027 – and one other 100 MW within the Promina challenge, in Croatia.

This content material is protected by copyright and might not be reused. If you need to cooperate with us and need to reuse a few of our content material, please contact: [email protected].