New grid connection guidelines in Romania – pv journal International


The Romanian Energy Regulatory Authority (ANRE) has adopted a number of adjustments to the grid connection processes, together with the implementation of an auction-based grid connection mechanism for crops above 5 MW from 2026 all the way in which ahead.

Romania’s National Energy Regulatory Authority (ANRE) has accredited a aggressive, auction-based mechanism for grid connections of latest crops of at the least 5 MW. The new rule will take impact on January 1, 2026.

The accredited process mirrors the method outlined in draft proposals revealed earlier this yr. It sees auctions held yearly, providing 10-year allocation intervals ranging from the second yr after the public sale.

Romania’s transmission system operator, Transelectrica, will decide and publish the accessible capability for every grid zone on January 15 of every yr. Then from July 1, Transelectrica will set up day by day public sale periods, with beginning costs calculated by dividing the full estimated worth of the grid improvement works by the full accessible grid capability.

George Niculsecu, president of ANRE, says that the brand new methodology “promotes a mechanism that ensures a aggressive setting that gives higher predictability within the vitality system.”

ANRE additionally made a number of adjustments instantly to the Romanian grid connection processes, together with new guidelines for monetary ensures. Previously required earlier than the completion of a connection, the assure is now a requirement for the issuance of any new grid connection allow above 1 MW and quantities to five% of the connection tariff.

The assure, which might be within the type of a financial institution assure, time period deposit, or direct cost, might be executed by the grid operator if the connection settlement will not be signed, the funds required underneath it usually are not made, the development allow can’t be obtained by the authorized deadline, the challenge will not be accomplished by the deadline of the connection settlement or the investor rejects the challenge.

The change will apply to all ongoing functions the place grid connection permits haven’t been granted, not simply potential candidates. Lawyers from Bucharest-based regulation agency Nyerges & Partners say the adjustments make the monetary assure “an environment friendly instrument that limits synthetic grid blockages attributable to tasks or these missing monetary sources.”

Other adjustments accredited by ANRE cowl grid calculations in the course of the challenge’s check section, mandate grid operators to submit month-to-month updates on the standing of the grid and supply 12-month extensions to building allow, situation of delays outdoors the management of buyers and a monetary assure of 5% of the connection tariff.

ANRE additionally ordered that any ongoing grid connection utility that has not been issued a allow shall be terminated on January 1, 2026, as the brand new public sale begins. “Since the completion time of the grid connection course of is basically outdoors the management of buyers and vital delays are frequent, this precept has a excessive threat for the initiation of latest investments,” stated these legal professional from Nyerges & Partners. “This obligation is anticipated to supply an incentive to grid operators to hurry up the connection course of.”

The Romanian Photovoltaic Industry Association says it expects the nation so as to add at the least 3 GW of renewables by 2026, with photo voltaic accounting for round 2 GW of the full. Statistics from the International Renewable Energy Agency present that Romania may have 1,414 MW of photo voltaic put in by the top of 2022.

In July, the Romanian parliament adopted a invoice that mandates prosumers with PV methods with a capability from 10.8 kW to 400 kW to put in vitality storage methods.