NextEra pitches Timberwolf Solar Project
Published 7:00 pm Tuesday, April 30, 2024
The photo voltaic panels are imagined to be on the bottom southern fringe of Taopi
A proposed NextEra Energy photo voltaic challenge, initially scheduled to start development close to Taopi in 2025 has been placed on maintain.
Naomi Morrison, the spokeswoman for NextEra Energy Resources confirmed final week that the challenge has been stopped however declined to present a cause why or if the challenge can be picked up once more at a later date.
“NextEra Energy Resources has determined to not proceed with a allow utility with the Minnesota Public Utilities Commission for the Timberwolf Solar challenge presently,” Morrison stated. “We stay dedicated to bringing vital financial advantages to the neighborhood and state of Minnesota with different renewable vitality initiatives.”
Mower County Board of Commissioners Chair John Mueller introduced that the 100 MW Timberwolf Solar Project has been placed on maintain through the board’s April 23 assembly.
He stated Monday that the corporate informed him they preserve the rights to the land they already acquired, “however they pulled their utility to the PUC.”
He added that it seems like NextEra will reverse their land claims.
The challenge, which can include 252,000 panels put in in 3,100 racks on 460 hectares of land from the southern fringe of Taopi, ought to begin development in May 2025 with a goal of August 2026 scheduled for completion. .
The photo voltaic array would have been linked to a small collector substation to be constructed subsequent to the Adams substation alongside Highway 56 east of Adams. There are additionally 190 toes of overhead transmission traces between the 2 websites.
Once the challenge is full, landowners will see an estimated $2 million yearly and $60 million on the finish of the challenge’s 30-year life.
The remaining challenge utility was submitted to the Minnesota Public Utilities Commission on October 30, 2023.